GLGridlinks SolutionsRequest a Quote

Service · Substation Design

Substation Design — AIS & GIS, 11 kV to 500 kV

Primary and secondary design for AIS and GIS substations from 11 kV to 500 kV.

The engineering problem

Network owners and developers need substation designs that pass utility review first time, interface cleanly with OEM equipment and can be built safely without late redesign. Gaps between primary, secondary and civil disciplines are the most common cause of rework and programme slip.

Capability

  • Primary design: single-line diagrams, general arrangements, sections, busbar and conductor sizing
  • Earthing grid design and step/touch potential assessment
  • Lightning protection and insulation coordination
  • Secondary design: protection, control and metering schematics, wiring and cable schedules
  • Auxiliary AC/DC supply design and battery sizing
  • Equipment specification, technical evaluation and vendor document review

Voltage / application

11 kV22 kV33 kV66 kV132 kV220 kV275 kV330 kV500 kV

Inputs — client data required

  • Network connection offer and fault levels
  • Site survey, geotechnical report and soil resistivity data
  • Client / utility design standards and preferred-equipment lists
  • Protection philosophy and SCADA point requirements
  • Environmental and planning constraints

Deliverables

  • Single-line and operating diagrams
  • General arrangement and section drawings
  • Earthing design report with step/touch results
  • Protection, control and wiring schematics
  • Cable schedules and bill of materials
  • Equipment specifications and technical schedules
  • Design report and IFC drawing set

Engineering software

  • AutoCAD / AutoCAD Electrical
  • CDEGS or equivalent for earthing
  • ETAP or DIgSILENT PowerFactory for supporting studies

Methodology

  1. Stage 1

    Concept

    Confirm connection requirements, layout options and key risks.

  2. Stage 2

    Preliminary design

    Develop SLD, GA and earthing concept; hold first SiD workshop.

  3. Stage 3

    Detailed design

    Complete primary and secondary packages and coordinate interfaces.

  4. Stage 4

    Issued for construction

    Final checks, utility approval and IFC release.

  5. Stage 5

    Construction support

    RFIs, design changes and as-built updates.

Design gates

30%

Concept and SLD agreed

60%

Layouts and earthing frozen

90%

Full package for utility review

IFC

Approved for construction

Verification — checker / approver model

  1. 1.Originator prepares the deliverable
  2. 2.Independent checker verifies calculations, drawings and assumptions
  3. 3.Discipline lead approves for issue
  4. 4.RPEQ / chartered engineer sign-off where required by jurisdiction or client

Standards

AS 2067IEEE 80IEC 61936-1AS/NZS 3000AS 1768IEC 61850AS/NZS 7000 (where line interface applies)

Utility requirements

  • DNSP connection and design standards (e.g. Ausgrid, Endeavour, Essential, Energex/Ergon, Powercor, SA Power Networks)
  • TNSP requirements (e.g. Transgrid, Powerlink, AusNet, ElectraNet, TasNetworks)
  • AEMO / National Electricity Rules Chapter 5 connection obligations
  • Network operator access, switching and permit-to-work rules

Quality controls

  • Design checklists per discipline
  • Drawing register with revision control
  • Inter-discipline check before each gate
  • Client and utility comments logged and closed out

HSE considerations

  • Safety in Design (SiD) workshops and hazard register
  • HV access, isolation and permit-to-work compliance
  • Safe Work Method Statements for high-risk construction work
  • Exclusion zones, step/touch potential and induced voltage controls

Cyber controls

  • Secure substation network architecture aligned to IEC 62351
  • Segregation of protection, control and corporate networks

Sustainability

  • Material efficiency and reduced site rework
  • Waste segregation and recycling on site
  • Embodied-carbon awareness in equipment selection
  • SF6-free or low-GWP switchgear options assessed where available

Asset lifecycle — ISO 55001 perspective

  • Design decisions recorded against asset life-cycle cost (ISO 55001)
  • Asset data and as-built records handed over in client asset-register format
  • Maintainability and spares strategy considered at design stage

Interfaces

  • Civil and structural
  • Protection and settings
  • SCADA and communications
  • OEM equipment suppliers
  • Transmission line / cable designers

Typical programme

Concept2–4 weeks
Preliminary design4–8 weeks
Detailed design8–16 weeks
Utility review and IFC2–6 weeks

Indicative only — actual programme depends on scope, approvals and outage windows.

Case studies

Technical FAQs

Do you design both AIS and GIS substations?

Yes. Layout, earthing and interface requirements differ, and we design both.

Can you work to our utility's standard designs?

Yes. We use the client or network operator's standards and preferred-equipment lists as the design basis.

Do you provide RPEQ sign-off?

Where required by the project or jurisdiction, design is signed off by a suitably registered engineer.

Capability datasheet

The Substation Design capability datasheet (PDF) is available on request.

Request datasheet

Discuss your project

Share voltage, scope and programme and an engineer will be in touch.

Discuss your project