Service · Substation Design
Substation Design — AIS & GIS, 11 kV to 500 kV
The engineering problem
Network owners and developers need substation designs that pass utility review first time, interface cleanly with OEM equipment and can be built safely without late redesign. Gaps between primary, secondary and civil disciplines are the most common cause of rework and programme slip.
Capability
- Primary design: single-line diagrams, general arrangements, sections, busbar and conductor sizing
- Earthing grid design and step/touch potential assessment
- Lightning protection and insulation coordination
- Secondary design: protection, control and metering schematics, wiring and cable schedules
- Auxiliary AC/DC supply design and battery sizing
- Equipment specification, technical evaluation and vendor document review
Voltage / application
Inputs — client data required
- Network connection offer and fault levels
- Site survey, geotechnical report and soil resistivity data
- Client / utility design standards and preferred-equipment lists
- Protection philosophy and SCADA point requirements
- Environmental and planning constraints
Deliverables
- Single-line and operating diagrams
- General arrangement and section drawings
- Earthing design report with step/touch results
- Protection, control and wiring schematics
- Cable schedules and bill of materials
- Equipment specifications and technical schedules
- Design report and IFC drawing set
Engineering software
- AutoCAD / AutoCAD Electrical
- CDEGS or equivalent for earthing
- ETAP or DIgSILENT PowerFactory for supporting studies
Methodology
Stage 1
Concept
Confirm connection requirements, layout options and key risks.
Stage 2
Preliminary design
Develop SLD, GA and earthing concept; hold first SiD workshop.
Stage 3
Detailed design
Complete primary and secondary packages and coordinate interfaces.
Stage 4
Issued for construction
Final checks, utility approval and IFC release.
Stage 5
Construction support
RFIs, design changes and as-built updates.
Design gates
30%
Concept and SLD agreed
60%
Layouts and earthing frozen
90%
Full package for utility review
IFC
Approved for construction
Verification — checker / approver model
- 1.Originator prepares the deliverable
- 2.Independent checker verifies calculations, drawings and assumptions
- 3.Discipline lead approves for issue
- 4.RPEQ / chartered engineer sign-off where required by jurisdiction or client
Standards
Utility requirements
- DNSP connection and design standards (e.g. Ausgrid, Endeavour, Essential, Energex/Ergon, Powercor, SA Power Networks)
- TNSP requirements (e.g. Transgrid, Powerlink, AusNet, ElectraNet, TasNetworks)
- AEMO / National Electricity Rules Chapter 5 connection obligations
- Network operator access, switching and permit-to-work rules
Quality controls
- Design checklists per discipline
- Drawing register with revision control
- Inter-discipline check before each gate
- Client and utility comments logged and closed out
HSE considerations
- Safety in Design (SiD) workshops and hazard register
- HV access, isolation and permit-to-work compliance
- Safe Work Method Statements for high-risk construction work
- Exclusion zones, step/touch potential and induced voltage controls
Cyber controls
- Secure substation network architecture aligned to IEC 62351
- Segregation of protection, control and corporate networks
Sustainability
- Material efficiency and reduced site rework
- Waste segregation and recycling on site
- Embodied-carbon awareness in equipment selection
- SF6-free or low-GWP switchgear options assessed where available
Asset lifecycle — ISO 55001 perspective
- Design decisions recorded against asset life-cycle cost (ISO 55001)
- Asset data and as-built records handed over in client asset-register format
- Maintainability and spares strategy considered at design stage
Interfaces
- Civil and structural
- Protection and settings
- SCADA and communications
- OEM equipment suppliers
- Transmission line / cable designers
Typical programme
| Concept | 2–4 weeks |
| Preliminary design | 4–8 weeks |
| Detailed design | 8–16 weeks |
| Utility review and IFC | 2–6 weeks |
Indicative only — actual programme depends on scope, approvals and outage windows.
Case studies
Technical FAQs
Do you design both AIS and GIS substations?
Yes. Layout, earthing and interface requirements differ, and we design both.
Can you work to our utility's standard designs?
Yes. We use the client or network operator's standards and preferred-equipment lists as the design basis.
Do you provide RPEQ sign-off?
Where required by the project or jurisdiction, design is signed off by a suitably registered engineer.
Capability datasheet
The Substation Design capability datasheet (PDF) is available on request.
Request datasheetDiscuss your project
Share voltage, scope and programme and an engineer will be in touch.