Engineering calculator

CT knee-point check

Required knee-point voltage of a protection CT to avoid saturation for maximum through-fault.

Inputs

Results

Secondary fault current
25A
Required knee-point
255V

Vk ≥ K × (If / N) × (Rct + 2Rlead + Rrelay)

Assumptions

  • 2Rlead assumes earth-fault loop; use Rlead for three-phase faults
  • K depends on X/R and relay manufacturer guidance

Limitations

  • Relay-specific requirements (e.g. differential, distance) override this generic check
  • Remanence and transient performance (IEC 61869-2 TPX/TPY) not modelled

References: IEC 61869-2 · AS 60044.1 (legacy)

Provided for general information. Gridlinks Solutions accepts no liability for decisions made using this calculator without independent engineering verification.